Lolo First 50 Road Decommissioning Project
The project proposes to decommission approximately 41 miles of unneeded Forest system roads and 25 miles of non-system skid trail/log jammer roads in the Lolo Creek watershed.
Project Summary
Location Summary:
The area lies about 12 miles east of Kamiah, Idaho in Idaho and Clearwater counties.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/04/2013 |
Comment Period | 08/01/2014 |
Objection Period Start | 02/11/2015 |
Decision | 04/2015 (Estimated) |
Implementation | 06/2015 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Nez Perce-Clearwater National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Watershed Management; Road Management
Project Activity:
Road Decommissioning
Current Status:
Completed
Project Decision Information
Lolo First 50 Road Decommissioning Project Final Decision Notice
Decision Signed Date: 04/07/2015
Forests:
Nez Perce-Clearwater National Forest
Districts:
Lochsa Ranger District
States:
Idaho
Counties:
Clearwater; Idaho
Legal Land Description:
T33N, R5E and R6E; T34N, R5E, R6E, R7E; T35N, R5E, R6E, and R7E; T36N, R5E, R6E and R7E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Karen Smith
104 Airport Road
Grangeville, ID 83530
208-935-4252
kasmith03@fs.fed.us
Last Updated: 10/25/2019