LOVCOM, INC. Amendment application for new replacement Tower
Installation of a new 80 foot self supported communications tower to replace an existing 40 foot tower to accommodate additional communication uses.
Project Summary
Current Status:
Completed
Location Summary:
Site is located approx. 1/4 mile from Forest Service Road 26 on Road 318, site known as the Bosin Rock Communications Site.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/06/2016 |
| Decision | 11/2016 (Estimated) |
| Implementation | 11/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bighorn National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
LOVCOM, INC. Amendment application for new replacement Tower
Decision Signed Date: 11/10/2016
Forests:
Bighorn National Forest
Districts:
Tongue Ranger District
States:
Wyoming
Counties:
Sheridan
Legal Land Description:
T.54N., R.85W., Section 29, 6th Principle Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Travis Fack
2013 Eastside 2nd Street
Sheridan, WY 82801
307-674-2683
tfack@fs.fed.us
Last Updated: 12/21/2016