Montana Dakota Utilities Underground Powerline Replacement
Permit Holder proposes to replace approx. 7025? underground powerline on NFS lands. Route will differ from existing line.
Project Summary
Location Summary:
Line will replace underground three phase 12.47kv electric line feeding the communication towers on Bosin Rock Communications Site and Blacktooth Subdivision and other cabins on Red Grade.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/01/2010 |
Decision | 11/2010 (Estimated) |
Implementation | 11/2010 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Powder River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Montana Dakota Utilities Special Use Permit Amendment #1
Decision Signed Date: 11/08/2010
Forests:
Bighorn National Forest
Districts:
Powder River Ranger District
States:
Wyoming
Counties:
Sheridan
Legal Land Description:
Sec. 28 and 29, T. 54N., R. 85W., 6th P.M.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Gayle Laurent
1415 Fort Street
Buffalo, WY 82834
307-674-2656
glaurent@fs.fed.us
Last Updated: 12/6/2010