Big Horn Rural Electric Co. Special Use Amendment #2
Install approximately 460 feet of underground powerline near Deer Haven Lodge to provide power to a Wyoming Department of Transportation weather station on US Highway 16.
Project Summary
Location Summary:
US Highway 16 near Deer Haven Lodge
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 09/19/2011 |
Decision | 10/2011 (Estimated) |
Implementation | 10/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Powder River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Big Horn Rural Electric Company Special Use Permit Amendment #2
Decision Signed Date: 10/18/2011
Forests:
Bighorn National Forest
Districts:
Powder River Ranger District
States:
Wyoming
Counties:
Big Horn
Legal Land Description:
T49N, R87W, Sec. 31
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Travis Fack
1415 Fort Street
Buffalo, WY 82834
307-674-2683
tfack@fs.fed.us
Last Updated: 11/7/2011