Buckskin Ed Creek/Trail 360 Stream Crossing Improvement
Replace the existing ford stream crossing with an OHV bridge to improve Yellowstone cutthroat trout habitat (sensitive species), by reducing trail erosion and aquatic sedimentation, and providing uninterrupted habitat for all aquatic organisms.
Project Summary
Location Summary:
Paint Rock Creek - south Paint Rock Creek 6th level watershed, where trail 360 crosses Buckskin Ed Creek.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/24/2014 |
Decision | 03/2014 (Estimated) |
Implementation | 08/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Bighorn National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants; Watershed Management; Recreation Management
Project Activity:
Species Habitat Improvements; Watershed Improvements
Current Status:
Completed
Project Decision Information
Buckskin Ed Creek - Trail 360 Stream Crossing Improvement
Decision Signed Date: 03/27/2014
Forests:
Bighorn National Forest
Districts:
Powder River Ranger District
States:
Wyoming
Counties:
Big Horn
Legal Land Description:
T50N R87W Section 27
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Chris Williams
2013 Eastside 2nd Street
Sheridan, WY 82801
307-674-2646
clwilliams@fs.fed.us
Last Updated: 4/29/2014