Southern Black Hills Water System Supplemental EA
The project is proposing to modify the original decision pertaining to the waterflow intake and water source as documented in the Decision Notice signed in 2012. The proposed action would allow for increased waterflow through the existing pipeline.
Project Summary
Location Summary:
Southern Black Hills -
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/01/2021 |
| Comment Period | 10/07/2021 |
| Objection Period Start | 12/17/2022 |
| Decision | 02/2023 (Estimated) |
| Implementation | 02/2023 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hell Canyon Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Southern Black Hills Water System Supplemental EA
Decision Signed Date: 02/10/2023
Forests:
Black Hills National Forest
Districts:
Hell Canyon Ranger District
States:
South Dakota
Counties:
Custer; Fall River
Legal Land Description:
T6S, R4E, Sec 24; T6S, R5E, Sec 19, 20, 29
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Wendy Schuyler
1019 N 5th Street
Custer, SD 57730
605-673-9361
wendy.schuyler@usda.gov
Last Updated: 2/23/2023