Pactola Planning Area
Project Planning Analysis - Vegetative Management to address insect (Mountain Pine Beetle) epidemic and fuels hazard concerns, prescibed fire/burning. HFRA Project.
Project Summary
Current Status:
Completed
Location Summary:
NFS lands around Pactola Lake and Silver City. Located approximately 5 miles north of Hill City and 10 miles east of Rapid City.
Project Milestones:
| Milestone | Date |
|---|---|
| NOI in Federal Register | 08/09/2010 |
| DEIS NOA in Federal Register | 05/06/2011 |
| FEIS NOA in Federal Register | 08/05/2011 |
| Objection Period Start | 08/06/2011 |
| Decision | 11/2011 (Estimated) |
| Implementation | 12/2011 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Hfra Title I: Threats To Ecosystem Components (Such As Insect Or Disease Epidemics)
Lead Management Unit:
Mystic Ranger District
Notice and Comment Regulation:
218
Project Purpose:
Fuels Management; Forest Products
Project Activity:
Timber Sales (Green)
Project Decision Information
Pactola Project Area
Decision Signed Date: 11/17/2011
Forests:
Black Hills National Forest
Districts:
Mystic Ranger District
States:
South Dakota
Counties:
Lawrence; Pennington
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Katie Van-Alstyne
8221 South Hwy 16
Rapid City, SD 57702
605-343-1567
kvanalstyne@fs.fed.us
Last Updated: 11/17/2011