White Elephant Mine Amendment
To amend the existing Plan of Operations for Pacer Corporation. Involves constructing an alterante access and loading area, reconstruct existing access. Some merchantable trees would need to be removed to clear the area.
Project Summary
Current Status:
Cancelled
Location Summary:
T4S R4E SE 1/4 Section 36
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/06/2013 |
| Decision | 06/2013 (Estimated) |
| Implementation | 08/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (10)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Black Hills National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Forests:
Black Hills National Forest
Districts:
Hell Canyon Ranger District
States:
South Dakota
Counties:
Custer
Legal Land Description:
T4S R4E SE1/4 of Section 36
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Gary Haag
1019 N. 5th Street
Custer, SD 57730
605-673-4853
ghaag@fs.fed.us
Last Updated: 6/12/2013