Hell Canyon Blowdown Salvage
Salvage of blowdown and storm damaged timber
Project Summary
Current Status:
Completed
Location Summary:
Pringle, SD area
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/25/2015 |
| Decision | 12/2015 (Estimated) |
| Implementation | 01/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (13), 36 Cfr 220.6(E)(13)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Black Hills National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Forest Products; Fuels Management; Road Management
Project Activity:
Timber Sales (Salvage)
Project Decision Information
Hell Canyon Blowdown Salvage
Decision Signed Date: 12/03/2015
Forests:
Black Hills National Forest
Districts:
Hell Canyon Ranger District
States:
South Dakota
Counties:
Custer
Legal Land Description:
T5S, R4E, Sections 3, 4, 9, 10, 18
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kelly Honors
1019 N. 5th Street
Custer, SD 57730
605-673-4853