Virginia Mine
Renewal of Plan of Operations for the Virginia Mine. The operator proposes to continue the mining of feldspar. The disturbed area is 3.5 acres. As part of the renewal the operator is proposing to expand the operation by an additional 0.25 acres.
Project Summary
Current Status:
Completed
Location Summary:
The project is located 9.75 miles south of Custer or 1.3 miles northeast of Pringle, SD.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/28/2015 |
| Decision | 10/2016 (Estimated) |
| Implementation | 11/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hell Canyon Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Project Decision Information
Virginia Mine
Decision Signed Date: 10/31/2016
Forests:
Black Hills National Forest
Districts:
Hell Canyon Ranger District
States:
South Dakota
Counties:
Custer
Legal Land Description:
Black Hills Meridian; T5S, R5E, NW1/4, SW 1/4, Section 7
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Gary Haag
1019 N 5th Street
Custer, SD 57730
605-673-9314
ghaag@fs.fed.us