Billy B Mine Plan of Operations
Rushmore Reserves, LLC, has acquired a mining claim for a quartz lode mine and has submitted a plan of operations to conduct mining operations on the previously mined claim. No additional area would be disturbed.
Project Summary
Current Status:
Completed
Location Summary:
T3N, R3E, Section 24. Minnesota Ridge area approximately 9 miles south of Deadwood, SD.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/14/2017 |
| Decision | 07/2017 (Estimated) |
| Implementation | 07/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Northern Hills Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Project Decision Information
Billy B Mine Plan of Operations
Decision Signed Date: 07/26/2017
Forests:
Black Hills National Forest
Districts:
Northern Hills Ranger District
States:
South Dakota
Counties:
Lawrence
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Karl Emanuel
2014 N. Main Street
Spearfish, SD 57783
605-642-4622
kemanuel@fs.fed.us