Rainbow Cave
Dr. Jim Mead is requesting authorization to continue excavations and research in the Rainbow Cave. The research will include excavating and removing material with bone and plant samples from the cave. Excavations will be screen
Project Summary
Current Status:
Completed
Location Summary:
Project is located at a Cave.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/10/2017 |
| Decision | 08/2018 (Estimated) |
| Implementation | 09/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hell Canyon Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations; Research And Development
Project Decision Information
Rainbow Cave
Decision Signed Date: 08/15/2018
Forests:
Black Hills National Forest
Districts:
Hell Canyon Ranger District
States:
South Dakota
Counties:
Custer
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Karina Hawley
1019 N 5th Street
Custer, SD 57730
605-673-9325
khawley@fs.fed.us
Last Updated: 9/6/2018