2019 Black Hills Energy Utility Line Rebuilds
Replacement of poles and utility lines along two corridors on the Northern Hills Ranger District. The Maitland corridor is located 4 miles south of Spearfish, SD and the Tinton corridor stretches from Savoy, SD to the area west of Iron Creek Lake.
Project Summary
Current Status:
Completed
Location Summary:
Along Maitland Road 4 miles south of Spearfish, SD and along the Tinton powerline corridor from Savoy, SD to west of Iron Creek Lake.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/27/2018 |
| Decision | 03/2019 (Estimated) |
| Implementation | 04/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Northern Hills Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management; Facility Management
Project Activity:
Electric Transmission; Facility Improvements/Construction
Project Decision Information
2019 Black Hills Energy Rebuilds: Maitland Line and Tinton Line
Decision Signed Date: 03/05/2019
Forests:
Black Hills National Forest
Districts:
Northern Hills Ranger District
States:
South Dakota
Counties:
Lawrence
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Callie Ackerman
2014 N. Main Street
Spearfish, SD 57783
605-642-4622
callieackerman@fs.fed.us
Last Updated: 3/5/2019