Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/18/2023 |
| Decision | 02/2023 (Estimated) |
| Implementation | 02/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mystic Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Project Decision Information
BHEC Mystic Rd. Overhead Powerline Relocation and New Underground Powerline Installation Project
Decision Signed Date: 02/08/2023
Forests:
Black Hills National Forest
Districts:
Mystic Ranger District
States:
South Dakota
Counties:
Pennington
Legal Land Description:
T.1N., R.4E., Sections 8 and 17, BHM, on National Forest System land
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Dona Warwick
8221 South Hwy 16
Rapid City, SD 57702
605-343-1567
dona.warwick@usda.gov
Last Updated: 2/9/2023