Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 11/12/2002 |
| Comment Period | 11/03/2003 |
| Decision | 08/2004 (Estimated) |
| Implementation | 03/2005 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Northern Hills Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Fuels Management; Forest Products; Road Management
Project Activity:
Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Road Improvements/Construction; Timber Sales (Green)
Project Decision Information
Riflepit Project
Decision Signed Date: 08/06/2004
Legal Notice Date: 08/16/2004
Forests:
Black Hills National Forest
Districts:
Northern Hills Ranger District
States:
South Dakota
Counties:
Lawrence
Legal Land Description:
T. 3N., R. 1E., Secs. 5-9, 15-22, 27-32; T. 4 N., R. 1E., Secs. 1-9, 16-20, 29-32
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Dave Atkins
2014 N. Main Street
Spearfish, SD 57783
605-642-4622
daatkins@fs.fed.us
Last Updated: 12/7/2009