Black Hills Electric Cooperative- High Plains Road Electric Service
BHEC to install new overhead power line to service private land along High Plains Road.
Project Summary
Location Summary:
Highplains Road via Pass Creek Road
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/12/2012 |
| Comment Period | 05/12/2012 |
| Decision | 06/2012 (Estimated) |
| Implementation | 06/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hell Canyon Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission
Current Status:
Completed
Project Decision Information
Decision Memo Overhead Power Line BHEC
Decision Signed Date: 06/15/2012
Legal Notice Date: 06/15/2012
Forests:
Black Hills National Forest
Districts:
Hell Canyon Ranger District
States:
South Dakota
Counties:
Custer
Legal Land Description:
Section 30, T4S, R3E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Laura Burns
1019 N 5th Street
Custer, SD 57730
605-673-4853
lburns@fs.fed.us
Last Updated: 6/18/2012