Deadwood-Agnew Mine Reclamation Project
The area to be reclaimed is approximately 4.4 acres. The mines open pit will be filled with a mica reclamation product that is produced at Pacer Corp. Once the pit is filled topsoil will be applied and the area will be seeded.
Project Summary
Location Summary:
The project is located approximately 1.5 miles west of Custer, SD and 0.2 miles south of US Hwy 16A
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/28/2013 |
| Comment Period | 06/28/2013 |
| Decision | 01/2014 (Estimated) |
| Implementation | 03/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hell Canyon Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Minerals And Geology
Project Activity:
Abandoned Mine Land Clean-Up
Current Status:
Completed
Project Decision Information
Deadwood-Agnew Mine Reclamation Project
Decision Signed Date: 01/14/2014
Forests:
Black Hills National Forest
Districts:
Hell Canyon Ranger District
States:
South Dakota
Counties:
Custer
Legal Land Description:
Black Hills Meridian, T3S, R5E, SE 1/4, Section 20
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Gary Haag
1019 N 5th Street
Custer, SD 57730
605-673-4853
ghaag@fs.fed.us
Last Updated: 6/26/2015