Phoenix 42 Placer Mining Project
Mining will consist of trenches approximately 150 ft. long x 50 ft. wide x 10 ft. deep. Gravels from the trenches will e processed through a trommel. Initially 5 yards of ore will be processed per hour. Mining will be conducted 10-12 hours per day.
Project Summary
Location Summary:
The project is along Upper French Creek approximately three-quarters of a mile west of the intersection of U.S. Highway 16 and County Road 286 (Upper French Creek Road). Access via existing access rd.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/13/2016 |
Decision | 09/2017 (Estimated) |
Implementation | 09/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hell Canyon Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
Phoenix 42 Placer Mining Project
Decision Signed Date: 09/28/2017
Forests:
Black Hills National Forest
Districts:
Hell Canyon Ranger District
States:
South Dakota
Counties:
Custer
Legal Land Description:
Black Hills Meridian, T.3S., R.4E., SE1/4 of Section 28
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Gary Haag
1019 N 5th Street
Custer, SD 57730
605-673-4853
ghaag@fs.fed.us