WBI Energy Transmission, Inc. Natural Gas Pipeline Special Use Permit Renewal
WBI Energy has operated a pipeline across NFS land since 1928. The existing permit expires on Dec. 31, 2020. WBI requested a renewal of the permit for an additional 30 years. All terms and conditions remain the same. No additional pipeline proposed.
Project Summary
Location Summary:
The pipeline runs from the city of Deadwood, SD north for approximately 2.2 miles to the National Forest boundary.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/03/2020 |
| Decision | 12/2020 (Estimated) |
| Implementation | 01/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Black Hills National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
WBI Energy Transmission, Inc. Natural Gas Pipeline Special Use Permit Renewal
Decision Signed Date: 12/08/2020
Forests:
Black Hills National Forest
Districts:
Northern Hills Ranger District
States:
South Dakota
Counties:
Lawrence
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Callie Ackerman-Jasper
1019 N. 5th Street
Custer, SD 57730
605-642-4622
Callie.Ackerman-Jasper@usda.gov
Last Updated: 1/5/2021