M.S. 1904 Utility Line Installation
Installation of an underground utility line. Three options for the path of the line are being evaluated, one of which will be selected for implementation.
Project Summary
Location Summary:
Approximately 4.6 miles southeast of Deadwood SD. About 1/10th mile northeast of the end of Country Club Road, Branch 1C
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/07/2021 |
| Decision | 08/2021 (Estimated) |
| Implementation | 08/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Northern Hills Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
M.S. 1904 Utility Line Installation
Decision Signed Date: 08/23/2021
Forests:
Black Hills National Forest
Districts:
Northern Hills Ranger District
States:
South Dakota
Counties:
Lawrence
Legal Land Description:
T4N R3E Section 19 NW 1/4 and T4N R3E Section 24 SW 1/4 BHM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Callie Ackerman-Jasper
2014 N. Main Street
Spearfish, SD 57783
605-642-4622
Callie.Ackerman-Jasper@usda.gov
Last Updated: 11/3/2021