DCP Douglas, LLC Natural Gas Pipeline to EOG Well
DCP will construct two 4inch natural gas pipelines; one high pressure steel line, one low pressure poly pipe, to the EOG-Arbalest 53-33H well to tie into their existing 4inch high pressure line. Less than 5 acres of NFS lands.
Project Summary
Current Status:
Completed
Location Summary:
Approximately 6 miles north of the Jenny Trail Hwy 59 Junction then approximately 3 miles east of Hwy 59.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/09/2011 |
| Decision | 01/2012 (Estimated) |
| Implementation | 02/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390)
Lead Management Unit:
Douglas and Thunder Basin Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Project Decision Information
DCP Douglas, LLC Proposed Natural Gas Pipeline To EOG Arbalest 53-33H Well
Decision Signed Date: 01/17/2012
Forests:
Medicine Bow-Routt National Forest
Districts:
Douglas and Thunder Basin Ranger District
States:
Wyoming
Counties:
Converse
Legal Land Description:
T41N, R72W, Sec 34 NW1/4NW1/4
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
James McKay
2250 East Richards Street
Douglas, WY 82633-8922
307-358-4690