EOG Resources Inc Road Permit
The Forest Services proposes to authorize EOG Resources, Inc to use portions of NFSRs 910, 910.D and 910.A and construct approximately 719 feet of new road in Section 18, and 190 feet in Section 15, T41N, R72W 6th PM to access proposed wells
Project Summary
Location Summary:
Approximately 21 miles north of Bill, WY along Hwy 59 and west of Hwy 59 approximately 4 miles
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/27/2011 |
Decision | 10/2011 (Estimated) |
Implementation | 11/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Forest Service Energy Implementation Plan
Lead Management Unit:
Douglas and Thunder Basin Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management; Special Use Management
Project Activity:
Special Use Authorizations; Road Improvements/Construction
Current Status:
Completed
Project Decision Information
EOG Resources, Inc. Road Construction and Reconstruction Permit
Decision Signed Date: 10/11/2011
Forests:
Medicine Bow-Routt National Forest
Districts:
Douglas and Thunder Basin Ranger District
States:
Wyoming
Counties:
Campbell
Legal Land Description:
Section 15, 17, 18, T41N R72W 6th PM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Hilaire Peck
2250 East Richards Street
Douglas, WY 82633-8922
307-358-7139
hwpeck@fs.fed.us