Highway 70 Road Reconstruction
The Wyoming Department of Transportation (WYDOT) is proposing to realign a portion of WYO Highway 70 between Baggs and Encampment, at reference marker (RM) 30.
Project Summary
Location Summary:
. The project is located in Carbon County within the Medicine Bow/Routt National Forest, 30 miles east of Baggs, 27 miles west of Encampment.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/15/2011 |
Comment Period | 02/15/2012 |
Decision | 03/2012 (Estimated) |
Implementation | 06/2012 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Brush Creek/Hayden Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Road Improvements/Construction
Current Status:
Completed
Project Decision Information
WYO 70 Dry Sandstone Slide
Decision Signed Date: 03/29/2012
Forests:
Medicine Bow-Routt National Forest
Districts:
Brush Creek/Hayden Ranger District
States:
Wyoming
Counties:
Carbon
Legal Land Description:
T. 87 W., R. 13 N. Section 9
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Diana Hood
2171 South Highway 130,
Saratoga, WY 82331
307-326-2507
dlhood@fs.fed.us
Last Updated: 3/29/2012