Gateway West Geotechnical Borings
Idaho Power and Rocky Mountain Power (the Companies) are conducting investigation and permitting activities necessary to construct transmission lines from the planned Windstar Substation in Converse County, Wyoming.
Project Summary
Location Summary:
Sensebaugh Canyon area
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/25/2012 |
| Decision | 07/2012 (Estimated) |
| Implementation | 08/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (8), 36 Cfr 220.6(D)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Douglas and Thunder Basin Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Gateway West Geotechnical Borings
Decision Signed Date: 07/25/2012
Forests:
Medicine Bow-Routt National Forest
Districts:
Douglas and Thunder Basin Ranger District
States:
Wyoming
Counties:
Natrona
Legal Land Description:
T30N, R78W Sec 13, NW1/4SE1/4 and Sec 23SE1/4SW1/4
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Misty Hays
2250 East Richards Street
Douglas, WY 82633-8922
307-358-7102