EOG Resources RUP for access to BT22E and BT22W
The proposed action is to issue a Road Use Permit for EOG Resources to use the existing road (0.4 mile in length). Also, to authorize EOG Resources to construct and maintain an access road would be a 269 foot long by 40 foot wide construction ROW.
Project Summary
Location Summary:
Approximately 12 miles south of the town of Wright, Wyoming and 3 miles west of Hwy. 59.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/24/2014 |
Decision | 08/2014 (Estimated) |
Implementation | 07/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Oil & Gas - Sec. 390, Energy Policy Act Of 2005 (Sec 390)
Lead Management Unit:
Douglas and Thunder Basin Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
EOG Resources, Inc Road Use Permit
Decision Signed Date: 08/12/2014
Forests:
Medicine Bow-Routt National Forest
Districts:
Douglas and Thunder Basin Ranger District
States:
Wyoming
Counties:
Campbell
Legal Land Description:
Section 14 T42N R72W and
Section 15 T42N R72W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Angela Bulla
2250 East Richards Street
Douglas, WY 82633-8922
307-358-7114
ambulla@fs.fed.us
Last Updated: 9/19/2014