High West Energy pole replacement
High West Energy requests to take out 14 power poles and replace them with 16 new power poles along the 1-80 corridor on the Pole Mountain unit.
Project Summary
Location Summary:
T. 14 N., R. 71 W., sec. 30
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/24/2014 |
Decision | 07/2014 (Estimated) |
Implementation | 09/2014 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Laramie Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
High West Energy Power Line Reconstruction
Decision Signed Date: 07/01/2014
Forests:
Medicine Bow-Routt National Forest
Districts:
Laramie Ranger District
States:
Wyoming
Counties:
Albany
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Nathan Haynes
3838 Cherrywood East Loop
Laramie, WY 82070-6535
307-828-5121
nhaynes@fs.fed.us
Last Updated: 9/11/2014