Wyoming Pipeline Company-Butte Junction Crude Oil Pipeline Replacement
The USFS is proposing to authorize Wyoming Pipeline Co to replace 3.2 miles of is existing crude oil pipeline. The work would require an additional 10 ft outside of the existing 20 ft ROW to complete construction activities.
Project Summary
Location Summary:
From the Butte Junction station to the soutwest side of Beaver Creek, west of Newcastle, WY
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/20/2014 |
| Comment Period | 08/20/2014 |
| Objection Period Start | 06/2015 (Estimated) |
| Decision | 07/2015 (Estimated) |
| Implementation | 07/2015 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Douglas and Thunder Basin Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Cancelled
Forests:
Medicine Bow-Routt National Forest
Districts:
Douglas and Thunder Basin Ranger District
States:
Wyoming
Counties:
Weston
Legal Land Description:
T44N, R63W Sec11, SE1/4 to T44N, R63W Sec 5 NE1/4
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
James McKay
2250 East Richards Street
Douglas, WY 82633-8922
307-358-4690
jmckay02@fs.fed.us
Last Updated: 11/20/2015