Powder River Energy Corporation (PRECorp) 69 kV Powerline Relocation at Black Thunder Mine
PRECorp proposal: installation of new 69kV 5-wire overhead powerline (treated wood poles, H-frame design, with raptor protection) and removal of old powerline to accommodate mine operation within the Black Thunder Mine permit area.
Project Summary
Location Summary:
Black Thunder Mine permit area.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/12/2015 |
Comment Period | 08/26/2015 |
Decision | 04/2016 (Estimated) |
Implementation | 04/2016 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Douglas and Thunder Basin Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Electric Transmission; Special Use Authorizations
Current Status:
Completed
Project Decision Information
69-kilovolt Powerline Relocation at Black Thunder Mine
Decision Signed Date: 04/15/2016
Forests:
Medicine Bow-Routt National Forest
Districts:
Douglas and Thunder Basin Ranger District
States:
Wyoming
Counties:
Campbell
Legal Land Description:
NE1/4 NW1/4, W1/2 W1/2 of Section 11 and NW1/4 NW1/4 of Section 14 in T43N, R71W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Misty Hays
2250 East Richards Street
Douglas, WY 82633-8922
307-358-4690
mahays@fs.fed.us
Last Updated: 4/24/2016