SourceGas Distribution, LLC Pipeline Permit Re-Issue
SourceGas Distribution, LLC has a Forest Service permit to operate/maintain a 2" polyethylene natural gas mainline located on the Brush Creek/Hayden Ranger District administrative site in Saratoga, WY. Permit is expired and needs to be renewed.
Project Summary
Location Summary:
NE1/4 Section 23, T. 17 N., R. 84 W. 6th P.M.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/16/2017 |
| Decision | 03/2018 (Estimated) |
| Implementation | 04/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Brush Creek/Hayden Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management; Facility Management
Project Activity:
Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance
Current Status:
Completed
Project Decision Information
SourceGas Distribution, LLC Pipeline Permit Re-Issue
Decision Signed Date: 03/26/2018
Forests:
Medicine Bow-Routt National Forest
Districts:
Brush Creek/Hayden Ranger District
States:
Wyoming
Counties:
Carbon
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Amber Horne
2171 South Highway 130,
Saratoga, WY 82331
307.326.2532
ahorne@fs.fed.us
Last Updated: 3/30/2018