William Williams Water Pipeline Permit Re-Issue
Re-issue of a Special Use permit for a 5-ft-long, 4-inch-wide pipeline that diverts water from a natural spring on National Forest lands onto private property.
Project Summary
Location Summary:
Section 10, T. 16 N., R. 80 W., 6th P.M.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/03/2017 |
Decision | 11/2017 (Estimated) |
Implementation | 12/2017 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (15)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Brush Creek/Hayden Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
William Williams Water Pipeline Permit Re-Issue
Decision Signed Date: 11/01/2017
Forests:
Medicine Bow-Routt National Forest
Districts:
Brush Creek/Hayden Ranger District
States:
Wyoming
Counties:
Carbon
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Amber Horne
2171 South Highway 130,
Saratoga, WY 82331
307.326.2532
ahorne@fs.fed.us
Last Updated: 3/30/2018