Hughes Power Line Project
Request from neighboring landowner to remove hazard trees that are on USFS lands that could hit a power line on his property.
Project Summary
Location Summary:
Approximately 6.5 roads miles southwest of the town of Encampment, Wyoming.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/08/2019 |
Decision | 07/2019 (Estimated) |
Implementation | 07/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (13), 36 Cfr 220.6(E)(13)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Brush Creek/Hayden Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Forest Products; Vegetation Management (Other Than Forest Products); Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels)
Current Status:
Completed
Project Decision Information
Hughes Power Line Decision Memo
Decision Signed Date: 07/15/2019
Forests:
Medicine Bow-Routt National Forest
Districts:
Brush Creek/Hayden Ranger District
States:
Wyoming
Counties:
Carbon
Legal Land Description:
N1/2,S32 T14N R84W,6th P.M.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Joshua Peck
2171 South Highway 130,
Saratoga, WY 82331
307-326-2518