Mountain Parks Electric Pole Replacement Project
This project proposes powerline maintenance,including the removal of 5 poles off of NFS lands and installation of 4 new poles on NFS lands. All work will be conducted over 12 inches or more of compacted snow.
Project Summary
Location Summary:
Near Lake Agnes and adjacent to Highway 40.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/21/2019 |
Decision | 01/2020 (Estimated) |
Implementation | 03/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Yampa Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Mountain Parks Electric Pole Replacement Project
Decision Signed Date: 01/09/2020
Forests:
Medicine Bow-Routt National Forest
Districts:
Yampa Ranger District
States:
Colorado
Counties:
Grand
Legal Land Description:
Township 5 North, Range 82 West, Sections 34 and 35, 6th P.M.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Janet Faller
300 Roselawn Ave
Yampa, CO 80483
970-870-2174
janet.faller@usda.gov
Last Updated: 3/28/2020