Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/03/2021 |
Decision | 09/2024 (Estimated) |
Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (21), 36 Cfr 220.6(E)(21)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Yampa Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Facility Management
Project Activity:
Facility Maintenance
Current Status:
Completed
Project Decision Information
Yampa Pipeline Maintenance
Decision Signed Date: 09/17/2024
Forests:
Medicine Bow-Routt National Forest
Districts:
Yampa Ranger District
States:
Colorado
Counties:
Routt
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kristopher Skinner
300 Roselawn Ave
Yampa, CO 80483
970-870-2299
Kristopher.Skinner@usda.gov
Last Updated: 9/23/2024