Road Use and Right-of-Way NFSR 1052
Right-of-way for commercial road use for mineral development of Laramide Fed oil well, operation, improvements, and maintenance of National Forest System Road 1052, 1052.A, and other connected system or non-system road.
Project Summary
Location Summary:
Thunder Basin NG - Spring Creek Unit, Spring Creek watershed, south of York Road and York Ranch approx. 1 mile.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/30/2023 |
Decision | 09/2023 (Estimated) |
Implementation | 11/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Douglas and Thunder Basin Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management; Special Use Management
Project Activity:
Special Use Authorizations; Road Maintenance; Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Road Use and Right-of-Way NFSR 1052
Decision Signed Date: 09/05/2023
Forests:
Medicine Bow-Routt National Forest
Districts:
Douglas and Thunder Basin Ranger District
States:
Wyoming
Counties:
Campbell
Legal Land Description:
Sec 5 T53N R69W, Sec 32 T54N R69W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Robena Downie
2250 East Richards Street
Douglas, WY 82633-8922
307-358-4690
Robena.Downie@usda.gov