Frazier and Lola Federal Oil Developments
Surface use plans for two fluid mineral development sites per Applications for Permit to Drill. Operator is Anschutz.
Project Summary
Location Summary:
Two well pads.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 11/30/2023 |
Decision | 04/2025 (Estimated) |
Implementation | 04/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (17), 36 Cfr 220.6(E)(17)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Douglas and Thunder Basin Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations; Natural Gas; Oil
Current Status:
Completed
Project Decision Information
Frazier and Lola Federal Oil Developments
Decision Signed Date: 04/15/2025
Forests:
Medicine Bow-Routt National Forest
Districts:
Douglas and Thunder Basin Ranger District
States:
Wyoming
Counties:
Campbell
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Kyle Schumacher
2250 East Richards Street
Douglas, WY 82633-8922
(307) 358-4690
Kyle.Schumacher@usda.gov
Last Updated: 4/21/2025