Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/08/2018 |
Comment Period | 03/28/2018 |
Objection Period Start | 02/07/2019 |
Decision | 05/2019 (Estimated) |
Implementation | 05/2019 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Leadville Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Developed Site Management; Special Use Authorizations; Timber Sales (Green)
Current Status:
Completed
Project Decision Information
Ski Cooper Way Back Pod Improvement
Decision Signed Date: 05/02/2019
Forests:
Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands
Districts:
Leadville Ranger District
States:
Colorado
Counties:
Lake
Legal Land Description:
T 8 S, R 80 W, Sec 17 - 19
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Michelle Mueggler
810 Front Street
Leadville, CO 80461
719-486-7409
mlmueggler@fs.fed.us
Last Updated: 7/25/2019