National Forest System Road (NFSR) 390 Reroute
A portion of NFSR 390 was damaged by spring 2019 runoff leaving the road unsafe for two-way vehicle travel. The FS proposes to reroute approx. 0.2 miles of road, install culverts and erosion control where needed in order to provide safe access.
Project Summary
Location Summary:
T. 12 S, R. 80 W, Sec. 15
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/26/2019 |
Comment Period | 12/26/2019 |
Decision | 04/2020 (Estimated) |
Implementation | 06/2020 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Leadville Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Road Management
Project Activity:
Road Maintenance; Road Improvements/Construction
Current Status:
Completed
Project Decision Information
National Forest System Road (NFSR) 390 Reroute
Decision Signed Date: 04/28/2020
Forests:
Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands
Districts:
Leadville Ranger District
States:
Colorado
Counties:
Lake
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jamie Krezelok
810 Front Street
Leadville, CO 80461
970-870-2256
jkrezelok@fs.fed.us
Last Updated: 6/11/2020