Special Use Authorization to Rebuild a 115kV Transmission Line, 9811
Proposal to amend the existing permit issued to Xcel Energy to approve actions to rebuild the existing transmission line. The BLM is lead agency. https://eplanning.blm.gov
Project Summary
Location Summary:
South east of Poncha Springs, Colorado
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/27/2022 |
| Comment Period | 08/08/2023 |
| Decision | 07/2024 (Estimated) |
| Implementation | 09/2024 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Salida Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
XCEL ENERGY%u2019S CIRCUIT 9811 115KV TRANSMISSION LINE REBUILD
Decision Signed Date: 07/01/2024
Forests:
Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands
Districts:
Salida Ranger District
States:
Colorado
Counties:
Chaffee
Legal Land Description:
Not Applicable
We're sorry, the documents for this project are not currently available. Please try again later.
Janine Prout
5575 Cleora Rd.
Salida, CO 81201
719-836-3866
janine.l.prout@usda.gov
Last Updated: 9/21/2024