Deweese Allotment Pipeline Project
Forest Service is proposing to authorize the Campo Grazing Association to install 10,560 feet of 1-1/4 inch PVC water pipeline in Unit 2 of the Deweese Allotment.
Project Summary
Location Summary:
Comanche National Grassland, near Baca County Road 25
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 08/03/2022 |
| Comment Period | 11/02/2022 |
| Decision | 03/2023 (Estimated) |
| Implementation | 03/2023 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Comanche Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Grazing Management
Project Activity:
Grazing Allotment Management; Grazing Structural Improvements
Current Status:
Completed
Project Decision Information
Deweese Allotment Pipeline Project
Decision Signed Date: 03/02/2023
Forests:
Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands
Districts:
Comanche Ranger District
States:
Colorado
Counties:
Baca
Legal Land Description:
T34S R46W Sec 20 NW SW and T34s R46W Sec 28 SE SW
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Nancy Brewer
P.O. Box 127
Spingfield, CO 81073
719-523-1706
nancy.brewer@usda.gov
Last Updated: 3/2/2023