DIR Uranium Exploratory Drilling Project
DIR Exploration, Inc. proposes to drill a maximum of 20 separate exploratory drill holes distributed over 7 different claims, or project areas.
Project Summary
Location Summary:
Claims are generally located at the southern end of the Tusayan District on both sides of Hwy 64.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/2009 (Estimated) |
Comment Period | 10/2009 (Estimated) |
Decision | 10/2010 (Estimated) |
Implementation | 05/2011 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Tusayan Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Cancelled
Forests:
Kaibab National Forest
Districts:
Tusayan Ranger District
States:
Arizona
Counties:
Coconino
Legal Land Description:
T27N, R4E, Sec. 6; T28N, R3E, Sec. 10; T28N, R4E, Sec. 12; T29N, R2E, Sec.13; T29N, R3E, Sec. 15, 26 & 30.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Thomas Mutz
176 Lincoln Log Loop
Grand Canyon, AZ 86023
928-635-5661
tmutz@fs.fed.us
Last Updated: 12/21/2009