Rainbow Rim Extension
The NKRD proposes to extend the existing Rainbow Rim trail east 8 miles. The first 4.5 miles will be new extension, and the remaining 3.5 mile will follow an existing decommisioned roadbed. The minimum tread wide of the new path will be 18-inches.
Project Summary
Location Summary:
Southwest corner of North Kaibab Ranger District.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/14/2012 |
Comment Period | 04/15/2012 |
Decision | 11/2012 (Estimated) |
Implementation | 11/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
North Kaibab Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
DECISION MEMO For RAINBOW RIM TRAIL EXTENSION PROJECT
Decision Signed Date: 11/01/2012
Legal Notice Date: 11/04/2012
Forests:
Kaibab National Forest
Districts:
North Kaibab Ranger District
States:
Arizona
Counties:
Coconino
Legal Land Description:
T34N, R1W, Section 1, and T35N, R1E, Sections 25, 26, 27, 31, 32, 33, 34, 35, and T35N, R1W, Section 36, G&SRBM.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Melissa Spandl
P.O. Box 248
Fredonia, AZ 86022
928-643-7395
mmspandl@fs.fed.us
Last Updated: 12/10/2019