CenturyLink Fiber Optic Line Installation
Installation of a fiber optic line within the existing Tranwestern ROW. ROW width of 8 feet. Lenght will equal 51,135 feet. Total of 9.391 acres
Project Summary
Location Summary:
Drake to Ashfork within Kaibab NF boundaries.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/29/2015 |
Decision | 01/2016 (Estimated) |
Implementation | 01/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Kaibab National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
CenturyLink Fiber Optic Line Installation
Decision Signed Date: 01/08/2016
Forests:
Kaibab National Forest
Districts:
Williams Ranger District
States:
Arizona
Counties:
Coconino; Yavapai
Legal Land Description:
T20N, R1W, Sec 19, 30; T20N, R2W, Sec 31; T21N, R1W, Sec 13, 24, 25; T21N, R2W, Sec 36.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Sheila Sandusky
800 South Sixth Street
Williams, AZ 86046
928-635-8275
ssandusky@fs.fed.us