East Ash Spring Exclosure
The Prescott National Forest proposes to construct a 0.5 acre exclosure and install a 10- to 2-foot pipeline extension from existing spring development to a small water drinker.
Project Summary
Location Summary:
East Ash Spring, Mingus Mountain area, Verde Ranger District
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/01/2011 |
| Decision | 08/2011 (Estimated) |
| Implementation | 02/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Verde Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements
Current Status:
Completed
Project Decision Information
East Ash Spring Exclosure Project
Decision Signed Date: 08/10/2011
Forests:
Prescott National Forest
Districts:
Verde Ranger District
States:
Arizona
Counties:
Yavapai
Legal Land Description:
T15N. R2E, Sec. 22, Hickey Mt quad
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Albert Sillas
300 East HWY 260
Camp Verde, AZ 86322
928-567-1124
asillas@fs.fed.us
Last Updated: 3/9/2012