Lower Wells Canyon Road Realignment Project
Realign 1.8 miles of the Lower Wells Canyon Road from Wells Canyon Creek drainage bottom onto the south facing slope to correct the continuous water resource impacts, provide the public with a safe travel route and reduce road maintenance costs.
Project Summary
Current Status:
Completed
Location Summary:
The project is in SE Idaho in Caribou County. It is located 20 miles southwest of Afton, Wyoming in the Crow Creek drainage.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/20/2022 |
| Comment Period | 01/20/2022 |
| Decision | 03/2022 (Estimated) |
| Implementation | 07/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (24), 36 Cfr 220.6(E)(24)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Montpelier Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management; Watershed Management
Project Activity:
Road Improvements/Construction; Watershed Improvements
Project Decision Information
Lower Wells Canyon Road Realignment
Decision Signed Date: 03/11/2022
Forests:
Caribou-Targhee National Forest
Districts:
Montpelier Ranger District
States:
Idaho
Counties:
Caribou
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Louis Wasniewski
322 North 4th Street
Montpelier, ID 83254
208-557-5783
louis.wasniewski@usda.gov
Last Updated: 3/11/2022