West Camas Riparian Improvement
The project intends to exclude livestock from riparian springs to restore riparian species and the springs natural flow regime. Troughs and wildlife friendly fences would be installed to prevent livestock trampling and grazing in the spring.
Project Summary
Location Summary:
The project is located north of West Camas Creek Rd, approximately 30 miles north of Dubois, ID.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/02/2024 |
| Decision | 09/2024 (Estimated) |
| Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Dubois Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management; Grazing Management
Project Activity:
Grazing Structural Improvements; Watershed Improvements
Current Status:
Completed
Project Decision Information
West Camas Riparian Improvement
Decision Signed Date: 09/24/2024
Forests:
Caribou-Targhee National Forest
Districts:
Dubois Ranger District
States:
Idaho
Counties:
Clark
Legal Land Description:
T13N, R4W, Section 4
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Keith Wheeler
98 North Oakley
Dubois, ID 83423
208-374-5422
keith.wheeler@usda.gov
Last Updated: 9/24/2024