Little Reservoir Pipeline Replacement
Existing pipeline that transfers water from the South Fork of Beaver River to Little Reservoir is deteriorating and needs to be replaced. Replacement pipe would be laid in the existing corridor.
Project Summary
Current Status:
Completed
Location Summary:
East of Little Reservoir to the South Fork of Beaver River
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/25/2011 |
| Decision | 11/2011 (Estimated) |
| Implementation | 01/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Beaver Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management; Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements; Watershed Improvements
Project Decision Information
Decision Memo Little Reservoir Pipeline Replacement
Decision Signed Date: 11/07/2011
Forests:
Fishlake National Forest
Districts:
Beaver Ranger District
States:
Utah
Counties:
Beaver
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Greyling Brandt
575 South Main St.
Beaver, UT 84713
218-663-8084
gbrandt@fs.fed.us