Boulder to Torrey SCC Fiber Optic Line
Fishlake and Dixie National Forests propose granting a special use permit to South Central Communications (SCC) for the construction and operation a fiber optic line which would run from Boulder to Torrey to increase telecommunications services.
Project Summary
Current Status:
Completed
Location Summary:
The fiber optic line will run from the intersection of 4690 N. and Highway 12 in Boulder and proceed north along Highway 12 to the junction of Highway 24 in Torrey in the existing road right-of-way.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/13/2019 |
| Decision | 11/2019 (Estimated) |
| Implementation | 06/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Fremont River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Boulder to Torrey SCC Fiber Optic Line
Decision Signed Date: 11/26/2019
Forests:
Fishlake National Forest
Districts:
Fremont River Ranger District
States:
Utah
Counties:
Garfield; Wayne
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Maggie Toone
138 South Main Street
Loa, UT 84747
435-896-1085
mtoone@fs.fed.us
Last Updated: 11/26/2019