Lakeside Marina Building Replacement
Fish Lake Resorts proposes to demolish their existing marina building and replace with one slightly larger (20' x 40')approximately 30 feet southeast of the existing building. A larger marina structure is needed to provide services for the marina.
Project Summary
Current Status:
Completed
Location Summary:
Fish Lake Basin at Lakeside Marina
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/09/2022 |
| Decision | 06/2022 (Estimated) |
| Implementation | 09/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Fremont River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Lakeside Marina Building Replacement
Decision Signed Date: 06/22/2022
Forests:
Fishlake National Forest
Districts:
Fremont River Ranger District
States:
Utah
Counties:
Sevier
Legal Land Description:
T26S R2E Section 19
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Maggie Toone
138 South Main Street
Loa, UT 84747
435-896-1085
maggie.toone@usda.gov
Last Updated: 6/22/2022