Pole Canyon
Promote aspen regeneration. Thin and salvage conifers.
Project Summary
Location Summary:
Half mile from Fish Lake approximately 10 miles north of Loa, UT
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/06/2009 |
Comment Period | 04/28/2010 |
Decision | 05/2021 (Estimated) |
Implementation | 05/2022 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Fremont River Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Vegetation Management (Other Than Forest Products)
Project Activity:
Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Salvage)
Current Status:
Cancelled
Project Decision Information
Decision Memo Pole Canyon Vegetation Treatment Project
Decision Signed Date: 12/09/2009
(FS Withdrawn, Reversed in Appeal (215))
Legal Notice Date: 12/16/2009
Forests:
Fishlake National Forest
Districts:
Fremont River Ranger District
States:
Utah
Counties:
Sevier
Legal Land Description:
T26S R2E S 13,14,15 and T26S R3E S18
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Terrance Holsclaw
138 South Main Street
Loa, UT 84747
435-896-1020
tholsclaw@fs.fed.us
Last Updated: 3/20/2018