Deer Trail Mine Exploration
The Beaver District of the Fishlake National Forest is proposing to authorize mining exploration to DT Mining, LLC, which consists of 13 exploration drill pads (with drill depths of approx. 5,000 ft.) near Deer Trail Mountain in the Tushar Range.
Project Summary
Location Summary:
Project activities would take place on the east side of the Tushar Mountain Range near Deer Trail Mountain between Twomile Creek and Cottonwood Creek, approximately 6 miles southwest of Marysvale, UT.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/20/2022 |
Comment Period | 04/20/2022 |
Decision | 09/2022 (Estimated) |
Implementation | 03/2023 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Beaver Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
Deer Trail Mine Exploration
Decision Signed Date: 09/26/2022
Forests:
Fishlake National Forest
Districts:
Beaver Ranger District
States:
Utah
Counties:
Piute
Legal Land Description:
Township 28 South, Range 4 West, Sections 10, 12, and 13
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Adam Solt
575 South Main St.
Beaver, UT 84713
435-896-1079
adam.solt@usda.gov
Last Updated: 9/27/2022